Each year, the City has been lining the sewer system to maintain its structural integrity and extend the service life of the pipe network.
In January 2019, City Council awarded a five-year bid contract to Granite/Inliner to perform this work.
Project Scope and Overview
Pipe candidates for lining are determined each year based on rating criteria from the regular sewer inspections.
Inliner will be notifying impacted residents via hand-delivered notices with contact information for the project.
QUESTIONS? Contact Project Manager Derrick Witz via email at derrick.witz@puriscorp.com or phone at 734-608-6009.
Project Start: April 2023
Project Completion: Late Fall 2023
Click here to view the map of this year's sewer linings.
To view the Project Map and Details 
The City of Berkley is continuing its multi-year, City-wide Sidewalk Replacement Program and Phase 4 will include the Southeast section of the City. This program will be taking a new approach where it will run in five-year cycles rather than carrying out replacements every 15 years. The shorter cycle between replacements is to ensure sidewalks no longer reach a point where they are unsafe for use.
Scope of the Program is as follows:
- Replacement of sidewalk slabs (whether they are the result of tree root disturbance or not) within the Southeast section of the City. This section is bordered by Woodward Avenue, Eleven Mile Road, Coolidge Highway, and Catalpa Road.
- Replacement of concrete slabs determined to be “immediate” (2 inches or more in vertical displacement/faulting).
Project Start: Summer/Fall of 2023
Project Completion: November 2023
To learn more about the sidewalk program scope or to see the FAQ's 
Project Scope and Overview
The scope of proposed improvements includes the removal and replacement of the existing asphalt road surface, new concrete curb and gutter, driveway approaches, sidewalks, ADA ramps and a new 8-inch public water main. Minimal trees may also be impacted by the project, and the City will work with the affected property owners on a replacement plan. In addition, minor stormwater drainage improvements are being evaluated.
Project Start: June 12, 2023
Project Completion: December 2023
To learn more about the project 